Organisers of the 2018 Winter Olympics in PyeongChang, South Korea, have updated Sports Management on the construction progress of the seven new competition venues and other facilities being built for the Games.

South Korean architecture, construction and engineering firm Taeyoung have designed the facilities for the Olympics, which will be gathered around two main mountain clusters – the Alpensia resort for the outdoor sports and the coastal city of Gangneung for the indoor events.

Five existing facilities will also be used to host events such as ski jumping and cross-country skiing.

A new high speed railway will be completed in June 2017 to link the sites with each other, the two Olympic villages being created for the Games, and Incehon Airport in Seoul.

Meanwhile, new spectator accommodation – including Richard Meier’s Seamarq Hotel and Planning Korea’s plankton-inspired Gangneung Resort Hotel – have been built to support the Games and regenerate the region.

Construction update for PyeongChang Mountain Cluster

Landscape architects SWA have masterplanned the cluster so that the new courses seemingly extend from their respective stadia into the surrounding terrain and adjacent unbuilt valleys. To maintain the natural beauty of the hilly forested site, the design team “pursued a compact, walkable development pattern, minimal grading, reforestation, and waterway restoration.”

They have also added practice ski jumps and a three-lift recreational ski area to the site. In summer, the stadia can be used for off-season training, while much of the terrain will become an 18-hole golf course.

Jeongseon Alpine Centre

Name: Jeongseon Alpine Centre
Sports: Alpine Skiing – Downhill, Super-G
Course length: 2,852m (Men), 2,388m (Women)
Capacity: 6,500
Construction progress: 69.5 per cent
Expected completion: October 2016
Consultant: former ski jumper Bernhard Russi

Alpensia Sliding Centre

Name: Alpensia Sliding Centre
Sports: Bobsleigh, Skeleton, Luge
Course length: 2,018m
Capacity: 7,500
Construction progress: 88.3 per cent
Expected completion: October 2016
Construction firm: Daelim

Olympic Plaza

Name: Olympic Plaza (for opening and closing ceremonies)
Capacity: 50,000 (temporary venue to be dismantled after the Games)
Construction progress: 14 per cent
Expected completion: September 2017

PyeongChang Olympic Village

Name: PyeongChang Olympic Village
Facilities: Hotels, restaurants, shops, entertainment venues and condominiums
Capacity: 3,500 athletes
Construction progress: 30 per cent
Expected completion: September 2017
Masterplan architect: Brent Thompson Architects

International Broadcasting Centre

Name: International Broadcasting Centre
Construction progress: 19.9 per cent
Expected completion: April 2017

Construction update for Gangneung Coastal Cluster

Gangneung Ice Arena

Name: Gangneung Ice Arena
Sports: Figure Skating, Short Track Speed Skating, Ice Dance
Capacity: 12,500
Construction progress: 91.4 per cent
Expected completion: November 2016

Gangneung Oval

Name: Gangneung Oval
Sports: Speed Skating
Capacity: 8,000
Construction progress: 73.4 per cent
Expected completion: January 2017

Gangneung Hockey Centre

Name: Gangneung Hockey Centre
Sports: Ice Hockey
Capacity: 10,000
Construction progress: 91.4 per cent
Expected completion: November 2016

Kwandong Hockey Centre

Name: Kwandong Hockey Centre
Sports: Ice Hockey
Capacity: 6,000
Construction progress: 93 per cent
Expected completion: October 2016

Gangneung Olympic Village

Name: Gangneung Olympic Village
Construction progress: 28 per cent
Expected completion: September 2017

Gangneung Media Village

Name: Gangneung Media Village
Construction progress: 32 per cent
Expected completion: September 2017

Existing facilities

• Alpensia Ski Jumping Centre
• Alpensia Biathlon Centre
• Alpensia Cross-Country Skiing Centre
• Yongpyong Alpine Centre
• Bokwang Snow Park
 


CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2024

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
 
Leisure Management - Winter Olympics organisers reveal progress of venue construction...
20 May 2024 Leisure Management: daily news and jobs
 
 
HOME
JOBS
NEWS
FEATURES
PRODUCTS
FREE DIGITAL SUBSCRIPTION
PRINT SUBSCRIPTION
ADVERTISE
CONTACT US
Sign up for FREE ezine
Latest news

06 Sep 2016

Winter Olympics organisers reveal progress of venue construction
BY Kim Megson

PyeongChang is hosting the 2018 Winter Olympics

PyeongChang is hosting the 2018 Winter Olympics
photo: Korean Culture and Information Service

Organisers of the 2018 Winter Olympics in PyeongChang, South Korea, have updated Sports Management on the construction progress of the seven new competition venues and other facilities being built for the Games.

South Korean architecture, construction and engineering firm Taeyoung have designed the facilities for the Olympics, which will be gathered around two main mountain clusters – the Alpensia resort for the outdoor sports and the coastal city of Gangneung for the indoor events.

Five existing facilities will also be used to host events such as ski jumping and cross-country skiing.

A new high speed railway will be completed in June 2017 to link the sites with each other, the two Olympic villages being created for the Games, and Incehon Airport in Seoul.

Meanwhile, new spectator accommodation – including Richard Meier’s Seamarq Hotel and Planning Korea’s plankton-inspired Gangneung Resort Hotel – have been built to support the Games and regenerate the region.

Construction update for PyeongChang Mountain Cluster

Landscape architects SWA have masterplanned the cluster so that the new courses seemingly extend from their respective stadia into the surrounding terrain and adjacent unbuilt valleys. To maintain the natural beauty of the hilly forested site, the design team “pursued a compact, walkable development pattern, minimal grading, reforestation, and waterway restoration.”

They have also added practice ski jumps and a three-lift recreational ski area to the site. In summer, the stadia can be used for off-season training, while much of the terrain will become an 18-hole golf course.

Jeongseon Alpine Centre

Name: Jeongseon Alpine Centre
Sports: Alpine Skiing – Downhill, Super-G
Course length: 2,852m (Men), 2,388m (Women)
Capacity: 6,500
Construction progress: 69.5 per cent
Expected completion: October 2016
Consultant: former ski jumper Bernhard Russi

Alpensia Sliding Centre

Name: Alpensia Sliding Centre
Sports: Bobsleigh, Skeleton, Luge
Course length: 2,018m
Capacity: 7,500
Construction progress: 88.3 per cent
Expected completion: October 2016
Construction firm: Daelim

Olympic Plaza

Name: Olympic Plaza (for opening and closing ceremonies)
Capacity: 50,000 (temporary venue to be dismantled after the Games)
Construction progress: 14 per cent
Expected completion: September 2017

PyeongChang Olympic Village

Name: PyeongChang Olympic Village
Facilities: Hotels, restaurants, shops, entertainment venues and condominiums
Capacity: 3,500 athletes
Construction progress: 30 per cent
Expected completion: September 2017
Masterplan architect: Brent Thompson Architects

International Broadcasting Centre

Name: International Broadcasting Centre
Construction progress: 19.9 per cent
Expected completion: April 2017

Construction update for Gangneung Coastal Cluster

Gangneung Ice Arena

Name: Gangneung Ice Arena
Sports: Figure Skating, Short Track Speed Skating, Ice Dance
Capacity: 12,500
Construction progress: 91.4 per cent
Expected completion: November 2016

Gangneung Oval

Name: Gangneung Oval
Sports: Speed Skating
Capacity: 8,000
Construction progress: 73.4 per cent
Expected completion: January 2017

Gangneung Hockey Centre

Name: Gangneung Hockey Centre
Sports: Ice Hockey
Capacity: 10,000
Construction progress: 91.4 per cent
Expected completion: November 2016

Kwandong Hockey Centre

Name: Kwandong Hockey Centre
Sports: Ice Hockey
Capacity: 6,000
Construction progress: 93 per cent
Expected completion: October 2016

Gangneung Olympic Village

Name: Gangneung Olympic Village
Construction progress: 28 per cent
Expected completion: September 2017

Gangneung Media Village

Name: Gangneung Media Village
Construction progress: 32 per cent
Expected completion: September 2017

Existing facilities

• Alpensia Ski Jumping Centre
• Alpensia Biathlon Centre
• Alpensia Cross-Country Skiing Centre
• Yongpyong Alpine Centre
• Bokwang Snow Park



Connect with
Leisure Management
Magazine:
View issue contents
Sign up:
Instant Alerts/zines

Print edition
 

News headlines
QC New York to unveil 15,000sq ft multimillion-dollar expansion in July
QC New York to unveil 15,000sq ft multimillion-dollar expansion in July   20 May 2024

QC New York, a luxury Italian day spa on Governors Island, will expand its offering this July by adding an extra 15,000sq ft of space. This new area .... more>>
1Rebel plans expansion following cash injection from Imbiba
1Rebel plans expansion following cash injection from Imbiba   20 May 2024

Leisure, lifestyle, wellness and entertainment growth investor, Imbiba, has invested in boutique gym brand, 1Rebel's holding company, One Rebel Ltd, .... more>>
PILAT3S to debut in ClubSportive, Amsterdam
PILAT3S to debut in ClubSportive, Amsterdam   20 May 2024

Urban Gym Group will launch PILAT3S at ClubSportive in Amsterdam next month, to create a boutique-in-gym experience. PILAT3S is the newly-launched .... more>>
Cedric Bryant is the new CEO at The American Council on Exercise
Cedric Bryant is the new CEO at The American Council on Exercise   20 May 2024

The American Council on Exercise has appointed Dr Cedric Bryant as its new CEO. Bryant takes up the new position on 1 July, following on from .... more>>
Wellness real estate market booming – forecast to reach $913bn by 2028, reports GWI
Wellness real estate market booming – forecast to reach $913bn by 2028, reports GWI   17 May 2024

The Global Wellness Institute (GWI) has released promising new research on the wellness real estate market at its third-annual Wellness Real Estate & .... more>>
Banyan Group appoints Paul Hawco to spearhead wellness strategy
Banyan Group appoints Paul Hawco to spearhead wellness strategy   14 May 2024

Paul Hawco, a seasoned figure in the international wellness industry, has assumed the role of executive director – integrated wellbeing at .... more>>
Company profile


Seed To Skin

Founded by Jeanette Thottrup in 2018, in Tuscany, Seed to Skin is an award winning skincare line.

View full profile>>

Catalogue gallery


Featured Supplier

Red Raion expands global presence with new Riyadh office

Red Raion expands global presence with new Riyadh office

Red Raion, the CGI studio for media-based attractions, has announced the opening of its new office in Riyadh, Saudi Arabia. More>>




in this issue

• Virgin gets right to wipe out rent arrears
• Fitness industry mourns passing of Jan Spaticchia
• STA offers mindfulness resources



Latest jobs

Jobs Search



Fitness Instructor
Salary: £23,144 to £25,138pa
Location: Moulsecoomb, Brighton and Hove, Brighton, UK
Company: University of Brighton
Duty Manager
Salary: Competitive
Location: Clevedon
Company: Everyone Active
Swim Teacher
Salary: Competitive
Location: Bristol
Company: Everyone Active
Diary dates
Powered by leisurediary.com

18-22 May 2024

Eco Resort Network

The Ravenala Attitude Hotel, Mauritius







Published by Leisure Media Tel: +44 (0)1462 431385 | Contact us | About us | © Cybertrek Ltd