NEWS
Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design
POSTED 14 Jan 2016 . BY Kim Megson
Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request Credit: Mary McCartney
Zaha Hadid Architects (ZHA) have claimed the Japan Sports Council are withholding payment for the studio’s design for the Japan National Stadium in Tokyo unless the architects give up the copyright to the designs and sign a confidentiality clause.

The revelations – confirmed to CLAD by the architects – mark the latest escalation in an increasingly bitter fallout between ZHA and the JSC over the decision to drop the architects from the 2020 Olympic stadium project in July 2015 over a dispute about the cost of the project.

Japanese architects Kengo Kuma have since been selected to design the 80,000 capacity stadium in Tokyo.

ZHA claims that the JSC has since sent it a revised agreement with a clause allowing the newly-selected design team to use any product of ZHA’s original work.

In a statement, the architects said: "We can confirm that we received and rejected a written request from the JSC to modify our existing contract to allow the transfer of the copyright of the detailed design for Japan National Stadium, owned by ZHA, in exchange for an overdue final payment.

“ZHA has also declined a request to sign an additional new contract clause requiring the design team to no longer provide information or comment on the project, in exchange for this outstanding payment being honoured.

“Since October, we have been seeking to finalise an outstanding payment with the JSC, which is for months of work carried out by a team of more than one hundred architects and engineers in Japan and the UK working for ZHA and many other companies.

“We welcome that the JSC has acknowledged the issue of the intellectual property for the fundamental and detailed elements of the stadium design. We hope that these matters can be quickly resolved."

In a further twist, ZHA has today (14 January) submitted a report to the JSC detailing what it claims are significant similarities between the structure, layout and numerous elements of their original design and Kengo Kuma’s new design.

The company said the document “will form the basis for the discussions we hope to resume shortly with the JSC to resolve the important issue of the use of valuable design work that is currently the copyright of ZHA and the original design team.”

After the decision to appoint Kengo Kuma in December, ZHA accused the Japanese authorities “and some of those from our own profession in Japan” of working together to make sure the original design was dropped.

In a statement released at the time, the studio said: “This shocking treatment of an international design and engineering team, as well as the respected Japanese design companies with whom we worked, was not about design or budget. In fact much of our two years of detailed work and the cost savings we recommended have been validated by the remarkable similarities of our original detailed stadium layout and our seating bowl configured with those of the [new] design.”

Amid the ongoing row, work on the National Stadium is expected to continue as planned. The new design will cost ¥149bn (£806m, US$1.2bn, €1.1bn) and is due to be completed by November 2019. It will be built by construction giant Taisei Corp.

Japanese prime minister Shinzo Abe said the new proposal was a “wonderful plan that meets criteria such as basic principles, construction period and cost”.
ZHA's original design for the stadium Credit: ZHA
The new design by Kengo Kuma's studio Credit: JSP
RELATED STORIES
  Zaha Hadid cries foul as Tokyo 2020 stadium design is chosen


Japanese architects Kengo Kuma have been selected to design the 80,000 capacity stadium which will be the centrepiece of the 2020 Olympics in Tokyo.
  Zaha Hadid Architects question Japanese government's logic for Olympic stadium designs


The architects of the original Tokyo 2020 Olympic stadium have accused the Japanese government of putting the legacy of the Games in jeopardy and overlooking several designers after it unveiled two new plans for the arena.
  Japan Sports Council unveils Olympic Stadium designs


Two stadium designs for the 2020 Tokyo Olympics have been revealed by the Japanese Sports Council.
  Zaha Hadid pulls out of Tokyo stadium competition citing inability to secure construction partner


Nikken Sekkei, which announced recently that it would partner with Zaha Hadid Architects to develop a proposal for the New National Stadium design and build competition for the Tokyo Olympics in 2020 has thrown in the towel.
 


CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2024

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
 
Leisure Management - Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design...
20 May 2024 Leisure Management: daily news and jobs
 
 
HOME
JOBS
NEWS
FEATURES
PRODUCTS
FREE DIGITAL SUBSCRIPTION
PRINT SUBSCRIPTION
ADVERTISE
CONTACT US
Sign up for FREE ezine
Latest news

14 Jan 2016

Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design
BY Kim Megson

Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request

Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request
photo: Mary McCartney

Zaha Hadid Architects (ZHA) have claimed the Japan Sports Council are withholding payment for the studio’s design for the Japan National Stadium in Tokyo unless the architects give up the copyright to the designs and sign a confidentiality clause.

The revelations – confirmed to CLAD by the architects – mark the latest escalation in an increasingly bitter fallout between ZHA and the JSC over the decision to drop the architects from the 2020 Olympic stadium project in July 2015 over a dispute about the cost of the project.

Japanese architects Kengo Kuma have since been selected to design the 80,000 capacity stadium in Tokyo.

ZHA claims that the JSC has since sent it a revised agreement with a clause allowing the newly-selected design team to use any product of ZHA’s original work.

In a statement, the architects said: "We can confirm that we received and rejected a written request from the JSC to modify our existing contract to allow the transfer of the copyright of the detailed design for Japan National Stadium, owned by ZHA, in exchange for an overdue final payment.

“ZHA has also declined a request to sign an additional new contract clause requiring the design team to no longer provide information or comment on the project, in exchange for this outstanding payment being honoured.

“Since October, we have been seeking to finalise an outstanding payment with the JSC, which is for months of work carried out by a team of more than one hundred architects and engineers in Japan and the UK working for ZHA and many other companies.

“We welcome that the JSC has acknowledged the issue of the intellectual property for the fundamental and detailed elements of the stadium design. We hope that these matters can be quickly resolved."

In a further twist, ZHA has today (14 January) submitted a report to the JSC detailing what it claims are significant similarities between the structure, layout and numerous elements of their original design and Kengo Kuma’s new design.

The company said the document “will form the basis for the discussions we hope to resume shortly with the JSC to resolve the important issue of the use of valuable design work that is currently the copyright of ZHA and the original design team.”

After the decision to appoint Kengo Kuma in December, ZHA accused the Japanese authorities “and some of those from our own profession in Japan” of working together to make sure the original design was dropped.

In a statement released at the time, the studio said: “This shocking treatment of an international design and engineering team, as well as the respected Japanese design companies with whom we worked, was not about design or budget. In fact much of our two years of detailed work and the cost savings we recommended have been validated by the remarkable similarities of our original detailed stadium layout and our seating bowl configured with those of the [new] design.”

Amid the ongoing row, work on the National Stadium is expected to continue as planned. The new design will cost ¥149bn (£806m, US$1.2bn, €1.1bn) and is due to be completed by November 2019. It will be built by construction giant Taisei Corp.

Japanese prime minister Shinzo Abe said the new proposal was a “wonderful plan that meets criteria such as basic principles, construction period and cost”.



Connect with
Leisure Management
Magazine:
View issue contents
Sign up:
Instant Alerts/zines

Print edition
 

News headlines
1Rebel plans expansion following cash injection from Imbiba
1Rebel plans expansion following cash injection from Imbiba   20 May 2024

Leisure, lifestyle, wellness and entertainment growth investor, Imbiba, has invested in boutique gym brand, 1Rebel's holding company, One Rebel Ltd, .... more>>
PILAT3S to debut in ClubSportive, Amsterdam
PILAT3S to debut in ClubSportive, Amsterdam   20 May 2024

Urban Gym Group will launch PILAT3S at ClubSportive in Amsterdam next month, to create a boutique-in-gym experience. PILAT3S is the newly-launched .... more>>
Cedric Bryant is the new CEO at The American Council on Exercise
Cedric Bryant is the new CEO at The American Council on Exercise   20 May 2024

The American Council on Exercise has appointed Dr Cedric Bryant as its new CEO. Bryant takes up the new position on 1 July, following on from .... more>>
Wellness real estate market booming – forecast to reach $913bn by 2028, reports GWI
Wellness real estate market booming – forecast to reach $913bn by 2028, reports GWI   17 May 2024

The Global Wellness Institute (GWI) has released promising new research on the wellness real estate market at its third-annual Wellness Real Estate & .... more>>
Banyan Group appoints Paul Hawco to spearhead wellness strategy
Banyan Group appoints Paul Hawco to spearhead wellness strategy   14 May 2024

Paul Hawco, a seasoned figure in the international wellness industry, has assumed the role of executive director – integrated wellbeing at .... more>>
Snap Fitness' holding company – Lift Brands – is up for sale
Snap Fitness' holding company – Lift Brands – is up for sale   13 May 2024

Speaking to HCM, global CEO of Lift Brands, Ty Menzies, has confirmed that the company – owner of Snap Fitness and Fitness On Demand – is up .... more>>
Company profile


miha bodytec

Founded in 2007 in Gersthofen, Germany, miha bodytec is the market-leading supplier of Electro Muscle Stimulation (EMS) equipment.

View full profile>>

Catalogue gallery


Featured Supplier

Red Raion expands global presence with new Riyadh office

Red Raion expands global presence with new Riyadh office

Red Raion, the CGI studio for media-based attractions, has announced the opening of its new office in Riyadh, Saudi Arabia. More>>




in this issue

• Virgin gets right to wipe out rent arrears
• Fitness industry mourns passing of Jan Spaticchia
• STA offers mindfulness resources



Latest jobs

Jobs Search



Fitness Instructor
Salary: £23,144 to £25,138pa
Location: Moulsecoomb, Brighton and Hove, Brighton, UK
Company: University of Brighton
Duty Manager
Salary: Competitive
Location: Clevedon
Company: Everyone Active
Swim Teacher
Salary: Competitive
Location: Bristol
Company: Everyone Active
Diary dates
Powered by leisurediary.com

18-22 May 2024

Eco Resort Network

The Ravenala Attitude Hotel, Mauritius







Published by Leisure Media Tel: +44 (0)1462 431385 | Contact us | About us | © Cybertrek Ltd