Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design
POSTED 14 Jan 2016 . BY Kim Megson
Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request Credit: Mary McCartney
Zaha Hadid Architects (ZHA) have claimed the Japan Sports Council are withholding payment for the studio’s design for the Japan National Stadium in Tokyo unless the architects give up the copyright to the designs and sign a confidentiality clause.

The revelations – confirmed to CLAD by the architects – mark the latest escalation in an increasingly bitter fallout between ZHA and the JSC over the decision to drop the architects from the 2020 Olympic stadium project in July 2015 over a dispute about the cost of the project.

Japanese architects Kengo Kuma have since been selected to design the 80,000 capacity stadium in Tokyo.

ZHA claims that the JSC has since sent it a revised agreement with a clause allowing the newly-selected design team to use any product of ZHA’s original work.

In a statement, the architects said: "We can confirm that we received and rejected a written request from the JSC to modify our existing contract to allow the transfer of the copyright of the detailed design for Japan National Stadium, owned by ZHA, in exchange for an overdue final payment.

“ZHA has also declined a request to sign an additional new contract clause requiring the design team to no longer provide information or comment on the project, in exchange for this outstanding payment being honoured.

“Since October, we have been seeking to finalise an outstanding payment with the JSC, which is for months of work carried out by a team of more than one hundred architects and engineers in Japan and the UK working for ZHA and many other companies.

“We welcome that the JSC has acknowledged the issue of the intellectual property for the fundamental and detailed elements of the stadium design. We hope that these matters can be quickly resolved."

In a further twist, ZHA has today (14 January) submitted a report to the JSC detailing what it claims are significant similarities between the structure, layout and numerous elements of their original design and Kengo Kuma’s new design.

The company said the document “will form the basis for the discussions we hope to resume shortly with the JSC to resolve the important issue of the use of valuable design work that is currently the copyright of ZHA and the original design team.”

After the decision to appoint Kengo Kuma in December, ZHA accused the Japanese authorities “and some of those from our own profession in Japan” of working together to make sure the original design was dropped.

In a statement released at the time, the studio said: “This shocking treatment of an international design and engineering team, as well as the respected Japanese design companies with whom we worked, was not about design or budget. In fact much of our two years of detailed work and the cost savings we recommended have been validated by the remarkable similarities of our original detailed stadium layout and our seating bowl configured with those of the [new] design.”

Amid the ongoing row, work on the National Stadium is expected to continue as planned. The new design will cost ¥149bn (£806m, US$1.2bn, €1.1bn) and is due to be completed by November 2019. It will be built by construction giant Taisei Corp.

Japanese prime minister Shinzo Abe said the new proposal was a “wonderful plan that meets criteria such as basic principles, construction period and cost”.
ZHA's original design for the stadium Credit: ZHA
The new design by Kengo Kuma's studio Credit: JSP
RELATED STORIES
  Zaha Hadid cries foul as Tokyo 2020 stadium design is chosen


Japanese architects Kengo Kuma have been selected to design the 80,000 capacity stadium which will be the centrepiece of the 2020 Olympics in Tokyo.
  Zaha Hadid Architects question Japanese government's logic for Olympic stadium designs


The architects of the original Tokyo 2020 Olympic stadium have accused the Japanese government of putting the legacy of the Games in jeopardy and overlooking several designers after it unveiled two new plans for the arena.
  Japan Sports Council unveils Olympic Stadium designs


Two stadium designs for the 2020 Tokyo Olympics have been revealed by the Japanese Sports Council.
  Zaha Hadid pulls out of Tokyo stadium competition citing inability to secure construction partner


Nikken Sekkei, which announced recently that it would partner with Zaha Hadid Architects to develop a proposal for the New National Stadium design and build competition for the Tokyo Olympics in 2020 has thrown in the towel.
 


CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2026

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
 
Leisure Management - Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design...
15 Jun 2026 Leisure Management: daily news and jobs
 
 
HOME
JOBS
NEWS
FEATURES
PRODUCTS
FREE DIGITAL SUBSCRIPTION
PRINT SUBSCRIPTION
ADVERTISE
CONTACT US
Sign up for FREE ezine
Latest news

14 Jan 2016

Zaha Hadid refuses to hand over copyright to Tokyo 2020 stadium design
BY Kim Megson

Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request

Zaha Hadid's studio have issued a strongly-worded statement in response to the copyright request
photo: Mary McCartney

Zaha Hadid Architects (ZHA) have claimed the Japan Sports Council are withholding payment for the studio’s design for the Japan National Stadium in Tokyo unless the architects give up the copyright to the designs and sign a confidentiality clause.

The revelations – confirmed to CLAD by the architects – mark the latest escalation in an increasingly bitter fallout between ZHA and the JSC over the decision to drop the architects from the 2020 Olympic stadium project in July 2015 over a dispute about the cost of the project.

Japanese architects Kengo Kuma have since been selected to design the 80,000 capacity stadium in Tokyo.

ZHA claims that the JSC has since sent it a revised agreement with a clause allowing the newly-selected design team to use any product of ZHA’s original work.

In a statement, the architects said: "We can confirm that we received and rejected a written request from the JSC to modify our existing contract to allow the transfer of the copyright of the detailed design for Japan National Stadium, owned by ZHA, in exchange for an overdue final payment.

“ZHA has also declined a request to sign an additional new contract clause requiring the design team to no longer provide information or comment on the project, in exchange for this outstanding payment being honoured.

“Since October, we have been seeking to finalise an outstanding payment with the JSC, which is for months of work carried out by a team of more than one hundred architects and engineers in Japan and the UK working for ZHA and many other companies.

“We welcome that the JSC has acknowledged the issue of the intellectual property for the fundamental and detailed elements of the stadium design. We hope that these matters can be quickly resolved."

In a further twist, ZHA has today (14 January) submitted a report to the JSC detailing what it claims are significant similarities between the structure, layout and numerous elements of their original design and Kengo Kuma’s new design.

The company said the document “will form the basis for the discussions we hope to resume shortly with the JSC to resolve the important issue of the use of valuable design work that is currently the copyright of ZHA and the original design team.”

After the decision to appoint Kengo Kuma in December, ZHA accused the Japanese authorities “and some of those from our own profession in Japan” of working together to make sure the original design was dropped.

In a statement released at the time, the studio said: “This shocking treatment of an international design and engineering team, as well as the respected Japanese design companies with whom we worked, was not about design or budget. In fact much of our two years of detailed work and the cost savings we recommended have been validated by the remarkable similarities of our original detailed stadium layout and our seating bowl configured with those of the [new] design.”

Amid the ongoing row, work on the National Stadium is expected to continue as planned. The new design will cost ¥149bn (£806m, US$1.2bn, €1.1bn) and is due to be completed by November 2019. It will be built by construction giant Taisei Corp.

Japanese prime minister Shinzo Abe said the new proposal was a “wonderful plan that meets criteria such as basic principles, construction period and cost”.



Connect with
Leisure Management
Magazine:
View issue contents
Sign up:
Instant Alerts/zines

Print edition
 

News headlines
Fitness Worx introduces blood testing
Fitness Worx introduces blood testing   15 Jun 2026

Independent operator, Fitness Worx Gyms, is introducing private blood testing as a service to members.

....
more>>
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways   15 Jun 2026

International industry lobbying associations are calling for physical activity and strength training to be deeply integrated with GLP-1 .... more>>

Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion
Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion   15 Jun 2026

Barons Eden, the UK parent company that operates luxury destination properties in England, has rebranded to become .... more>>

Les Mills calls on the industry to support UNICEF
Les Mills calls on the industry to support UNICEF   12 Jun 2026

Global group exercise specialist, Les Mills, is inviting operators to sign up to its Workout for the World event on 20 June, in support of .... more>>

Belgin Aksoy marks 15 years of Global Wellness Day
Belgin Aksoy marks 15 years of Global Wellness Day   12 Jun 2026

Global Wellness Day (GWD) marked its 15th anniversary on Saturday 13 June 2026, with the theme: #JoyMagenta – a celebration of the healing .... more>>

HUM2N launches longevity clinic at Six Senses London
HUM2N launches longevity clinic at Six Senses London   12 Jun 2026

Global luxury hospitality brand, Six Senses, has partnered with longevity healthcare provider, HUM2N, to launch a clinic at Six Senses London, at .... more>>

Company profile


Technogym UK Ltd

Founded in 1983, Technogym is a world leader brand in fitness, wellness, sport and health.

View full profile>>

Catalogue gallery


Featured Supplier

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Sun protection is no longer just about shielding the skin – it's about enhancing it. More>>




in this issue

• Virgin gets right to wipe out rent arrears
• Fitness industry mourns passing of Jan Spaticchia
• STA offers mindfulness resources



Latest jobs

Jobs Search



Community Activator Coach Apprentice
Salary: 16,686
Location: Stowmarket, Suffolk
Company: Everyone Active
Membership Advisor
Salary: Competitive salary plus commission & benefits
Location: Market Rasen
Company: Everyone Active
Customer Service Advisor
Salary: Competitive
Location: Market Rasen
Company: Everyone Active
Diary dates
Powered by leisurediary.com

15-18 Jun 2026

HLTH Europe

RAI Convention Centre, Amsterdam, Netherlands







Published by Leisure Media Tel: +44 (0)1462 431385 | Contact us | About us | © Cybertrek Ltd