NEWS
Minnesota Vikings move into US$1bn stadium
POSTED 22 Jun 2016 . BY Kim Megson
The 70,000-capacity stadium cost US$1.1bn to build Credit: Minnesota Vikings
The new home of American National Football League (NFL) franchise the Minnesota Vikings has been completed six weeks ahead of schedule in Minneapolis.

Contractor Mortenson Construction has symbolically handed over the keys to the U.S. Bank Stadium to the Vikings and the building’s owner, the Minnesota Sports Facilities Authority (MSFA).

Designed by HKS Architects, the 70,000-capacity stadium cost US$1.1bn (€974m, £749m) to build. The 1.75m sq ft (162,600sq m) structure features a fixed-roof design with the largest span of transparent ETFE material in the country, five vast glass pivoting doors, and the closest seats to the field in the NFL.

Other features include two concourses with 360-degree circulation and various views into the bowl; LED lighting; 2,000 HD flat screen TVs to replay the action from the field; and stairs, ramps, escalators and elevators connecting the venue’s seven levels. A giant stylised Legacy Ship also stands outside the ground.

A Vikings Stadium Consortium made up of local firms Studio Hive, Studio Five and Lawal Scott Erickson Architects collaborated with HKS on the design.

As part of a partnership deal agreed with curators Sports & The Arts (SATA), the stadium will display more than 500 original artworks and photography showcasing the history of Vikings and Minnesota sports.

“Mortenson Construction has done a phenomenal job keeping us ahead of schedule while building the most amazing stadium in the United States,” said Michele Kelm-Helgen, chair of the MSFA.

“This is an incredible feat by HKS, Mortenson Construction, the MSFA and the Vikings, as well as the hundreds of subcontractors and thousands of Minnesota men and women who worked on this project over the last two and a half years,” said Vikings owner Mark Wilf.

“U.S. Bank Stadium was designed with the fan experience as the number one priority, and to accomplish this milestone ahead of schedule is a testament to the talent and dedication by so many.”

The stadium was built in two-and-a-half years, with more than 8,000 workers committing more than four million hours to the project.

The final cleanup of the site is now taking place before the grand opening ceremony is held on 22 July. The first sporting event the venue will host will be a friendly fixture between football sides AC Milan and Chelsea on 3 August. Two weeks later Metallica will become the first band to perform there.

The stadium has also been announced as the home of the 2018 Super Bowl.

The Vikings recently put forward a proposal to build new headquarters with training facilities and a 6,000-capacity training stadium in north-east Eagan, Minnesota.
The 1.75m sq ft structure features a fixed-roof design with the largest span of transparent ETFE material in the country Credit: Minnesota Vikings
The stadium is a new landmark for Minneapolis Credit: Minnesota Vikings
RELATED STORIES
  Minnesota Vikings plan HQ development with 6,000-capacity stadium


National Football League (NFL) franchise Minnesota Vikings has put forward a proposal to build new headquarters with training facilities and a 6,000-capacity stadium.
  Minnesota Vikings set sail with replica ship featuring 2,000sq ft LED screen


A 2,000sq ft (186sq m) curved LED screen will be one of the features of a giant stylised ship which is due to be built outside the home of the Minnesota Vikings.
  New Minnesota Vikings stadium to display 500 works of art


The US Bank Stadium – the new home of the Minnesota Vikings currently under construction in Minneapolis, US – is set to boast an art collection to rival some museums.
  New Vikings Stadium to host 2018 NFL Super Bowl


The construction of the new Minnesota Vikings stadium has been given a further boost after the venue was awarded the 2018 NFL Super Bowl.
 


CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2026

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
 
Leisure Management - Minnesota Vikings move into US$1bn stadium ...
15 Jun 2026 Leisure Management: daily news and jobs
 
 
HOME
JOBS
NEWS
FEATURES
PRODUCTS
FREE DIGITAL SUBSCRIPTION
PRINT SUBSCRIPTION
ADVERTISE
CONTACT US
Sign up for FREE ezine
Latest news

22 Jun 2016

Minnesota Vikings move into US$1bn stadium
BY Kim Megson

The 70,000-capacity stadium cost US$1.1bn to build

The 70,000-capacity stadium cost US$1.1bn to build
photo: Minnesota Vikings

The new home of American National Football League (NFL) franchise the Minnesota Vikings has been completed six weeks ahead of schedule in Minneapolis.

Contractor Mortenson Construction has symbolically handed over the keys to the U.S. Bank Stadium to the Vikings and the building’s owner, the Minnesota Sports Facilities Authority (MSFA).

Designed by HKS Architects, the 70,000-capacity stadium cost US$1.1bn (€974m, £749m) to build. The 1.75m sq ft (162,600sq m) structure features a fixed-roof design with the largest span of transparent ETFE material in the country, five vast glass pivoting doors, and the closest seats to the field in the NFL.

Other features include two concourses with 360-degree circulation and various views into the bowl; LED lighting; 2,000 HD flat screen TVs to replay the action from the field; and stairs, ramps, escalators and elevators connecting the venue’s seven levels. A giant stylised Legacy Ship also stands outside the ground.

A Vikings Stadium Consortium made up of local firms Studio Hive, Studio Five and Lawal Scott Erickson Architects collaborated with HKS on the design.

As part of a partnership deal agreed with curators Sports & The Arts (SATA), the stadium will display more than 500 original artworks and photography showcasing the history of Vikings and Minnesota sports.

“Mortenson Construction has done a phenomenal job keeping us ahead of schedule while building the most amazing stadium in the United States,” said Michele Kelm-Helgen, chair of the MSFA.

“This is an incredible feat by HKS, Mortenson Construction, the MSFA and the Vikings, as well as the hundreds of subcontractors and thousands of Minnesota men and women who worked on this project over the last two and a half years,” said Vikings owner Mark Wilf.

“U.S. Bank Stadium was designed with the fan experience as the number one priority, and to accomplish this milestone ahead of schedule is a testament to the talent and dedication by so many.”

The stadium was built in two-and-a-half years, with more than 8,000 workers committing more than four million hours to the project.

The final cleanup of the site is now taking place before the grand opening ceremony is held on 22 July. The first sporting event the venue will host will be a friendly fixture between football sides AC Milan and Chelsea on 3 August. Two weeks later Metallica will become the first band to perform there.

The stadium has also been announced as the home of the 2018 Super Bowl.

The Vikings recently put forward a proposal to build new headquarters with training facilities and a 6,000-capacity training stadium in north-east Eagan, Minnesota.



Connect with
Leisure Management
Magazine:
View issue contents
Sign up:
Instant Alerts/zines

Print edition
 

News headlines
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways   15 Jun 2026

International industry lobbying associations are calling for physical activity and strength training to be deeply integrated with GLP-1 .... more>>

Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion
Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion   15 Jun 2026

Barons Eden, the UK parent company that operates luxury destination properties in England, has rebranded to become .... more>>

Les Mills calls on the industry to support UNICEF
Les Mills calls on the industry to support UNICEF   12 Jun 2026

Global group exercise specialist, Les Mills, is inviting operators to sign up to its Workout for the World event on 20 June, in support of .... more>>

Belgin Aksoy prepares to mark 15 years of Global Wellness Day on Saturday 13 June
Belgin Aksoy prepares to mark 15 years of Global Wellness Day on Saturday 13 June   12 Jun 2026

Global Wellness Day (GWD) will mark its 15th anniversary on Saturday 13 June 2026, with the theme: #JoyMagenta – a celebration of the healing .... more>>

HUM2N launches longevity clinic at Six Senses London
HUM2N launches longevity clinic at Six Senses London   12 Jun 2026

Global luxury hospitality brand, Six Senses, has partnered with longevity healthcare provider, HUM2N, to launch a clinic at Six Senses London, at .... more>>

Mayrlife opens first hotel day clinic in partnership with Rosewood Vienna
Mayrlife opens first hotel day clinic in partnership with Rosewood Vienna   11 Jun 2026

As part of its first hotel partnership, Mayrlife – the medical health resort company known for its site in Altaussee, Austria – has launched a day .... more>>

Company profile


Life Fitness/Hammer Strength

Life Fitness / Hammer Strength works with some of the world’s most recognised hospitality brands, supporting premium fitness experiences.

View full profile>>

Catalogue gallery


Featured Supplier

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Sun protection is no longer just about shielding the skin – it's about enhancing it. More>>




in this issue

• Virgin gets right to wipe out rent arrears
• Fitness industry mourns passing of Jan Spaticchia
• STA offers mindfulness resources



Latest jobs

Jobs Search



Community Activator Coach Apprentice
Salary: 16,686
Location: Stowmarket, Suffolk
Company: Everyone Active
Membership Advisor
Salary: Competitive salary plus commission & benefits
Location: Market Rasen
Company: Everyone Active
Customer Service Advisor
Salary: Competitive
Location: Market Rasen
Company: Everyone Active
Diary dates
Powered by leisurediary.com

15-18 Jun 2026

HLTH Europe

RAI Convention Centre, Amsterdam, Netherlands







Published by Leisure Media Tel: +44 (0)1462 431385 | Contact us | About us | © Cybertrek Ltd