NEWS
Defiant Kuma's Tokyo Olympic Stadium granted green light
POSTED 03 Oct 2016 . BY Kim Megson
Kuma's design for the stadium uses large amounts of wood to reference Japan's 'age of maturity' Credit: Taisei Corporation, Azusa Sekkei Co., Ltd. and Kengo Kuma and Associates
Credit: Kengo Kuma and Associates
Slowdown [in Japan] is creating new types of culture, new types of lifestyle. For the stadium, I have used a lot of wood because I think it’s an appropriate material to symbolise this change.
– Kengo Kuma
The Japanese government has approved a 150bn yen ($1.5bn, €1.3bn, £1.1bn) contract allowing work to begin on Kengo Kuma’s 2020 Tokyo Olympic Stadium.

Construction is scheduled to begin in December. The government-funded Japan Sport Council (JSC), which is overseeing the project, estimates that construction will be completed at the end of November 2019 – five months behind the original schedule.

New Tokyo Governor Yuriko Koike said she would closely monitor the project, which the city is part-funding. “For the burden we have to share, I will ensure it’s utilised for the people of Tokyo, and raise my voice when necessary,” she was quoted as saying by local media.

The project green light looks to have finally ended a protracted and public saga, which saw a design team led by Zaha Hadid Architects (ZHA) awarded and then stripped of the project amid spiralling costs, accusations and acrimony.

Kuma was then appointed to complete a new design after the JSC were swayed by his vision for a predominantly wooden, tree-surrounded stadium. However, ZHA accused his plans of sharing “remarkable similarities with our original detailed stadium layout and our seating bowl [configuration].”

ZHA director Patrik Schumacher later described the whole saga as “incredibly distressing” and "the biggest setback ever."

In an exclusive interview with CLAD, which will appear in the forthcoming issue of CLADmag, Kuma defended his design and said that while there are some “unavoidable” similarities – such as the evacuation points, the position of the stairs and the layout of the field – his vision for the project “is totally opposite” the one proposed by ZHA.

“The communication between Zaha, the Japanese partners and the client was very bad,” he said. “I think it’s a problem in Japan. For foreign architects to work here is not easy because the system is totally different and a language barrier exists between the Japanese and the foreigners.

“Zaha was very much frustrated with that kind of miscommunication. I understand that difficulty, of course. But I was not happy to hear the claims about our scheme.”

The Japanese architect said his stadium, and the 2020 Games more broadly, will symbolise today’s Japan: a country “whose culture and direction is totally opposite from what went before” due to a slowing down of both economic growth and the pace of life.

“This new direction can be called the age of maturity,” he said. “People are finding a new, slower kind of lifestyle. But slowdown is not bad. Slowdown is creating new types of culture, new types of lifestyle. For the stadium, I have used a lot of wood because I think it’s an appropriate material to symbolise this change.”
RELATED STORIES
  Japan Sports Council reveals cost of abandoning Zaha Hadid's Tokyo stadium design


The body in charge of organising Tokyo’s Olympic Games has admitted its decision to cancel Zaha Hadid Architects’ (ZHA) National Olympic Stadium design in favour of a cheaper alternative has already cost it ¥68.6bn (US$650.6m, €582.4m, £497m) in compensation payouts.
  Kengo Kuma hits back in Tokyo 2020 stadium row


The architect developing Japan’s National Stadium for the Tokyo 2020 Olympic Games has publicly refuted claims his studio have copied from an earlier design submitted by Zaha Hadid Architects.
  Zaha Hadid cries foul as Tokyo 2020 stadium design is chosen


Japanese architects Kengo Kuma have been selected to design the 80,000 capacity stadium which will be the centrepiece of the 2020 Olympics in Tokyo.
  Zaha Hadid pulls out of Tokyo stadium competition citing inability to secure construction partner


Nikken Sekkei, which announced recently that it would partner with Zaha Hadid Architects to develop a proposal for the New National Stadium design and build competition for the Tokyo Olympics in 2020 has thrown in the towel.
 


CONTACT US

Leisure Media
Tel: +44 (0)1462 431385

©Cybertrek 2026

ABOUT LEISURE MEDIA
LEISURE MEDIA MAGAZINES
LEISURE MEDIA HANDBOOKS
LEISURE MEDIA WEBSITES
LEISURE MEDIA PRODUCT SEARCH
PRINT SUBSCRIPTIONS
FREE DIGITAL SUBSCRIPTIONS
 
Leisure Management - Defiant Kuma's Tokyo Olympic Stadium granted green light...
15 Jun 2026 Leisure Management: daily news and jobs
 
 
HOME
JOBS
NEWS
FEATURES
PRODUCTS
FREE DIGITAL SUBSCRIPTION
PRINT SUBSCRIPTION
ADVERTISE
CONTACT US
Sign up for FREE ezine
Latest news

03 Oct 2016

Defiant Kuma's Tokyo Olympic Stadium granted green light
BY Kim Megson

Kuma's design for the stadium uses large amounts of wood to reference Japan's 'age of maturity'

Kuma's design for the stadium uses large amounts of wood to reference Japan's 'age of maturity'
photo: Taisei Corporation, Azusa Sekkei Co., Ltd. and Kengo Kuma and Associates

The Japanese government has approved a 150bn yen ($1.5bn, €1.3bn, £1.1bn) contract allowing work to begin on Kengo Kuma’s 2020 Tokyo Olympic Stadium.

Construction is scheduled to begin in December. The government-funded Japan Sport Council (JSC), which is overseeing the project, estimates that construction will be completed at the end of November 2019 – five months behind the original schedule.

New Tokyo Governor Yuriko Koike said she would closely monitor the project, which the city is part-funding. “For the burden we have to share, I will ensure it’s utilised for the people of Tokyo, and raise my voice when necessary,” she was quoted as saying by local media.

The project green light looks to have finally ended a protracted and public saga, which saw a design team led by Zaha Hadid Architects (ZHA) awarded and then stripped of the project amid spiralling costs, accusations and acrimony.

Kuma was then appointed to complete a new design after the JSC were swayed by his vision for a predominantly wooden, tree-surrounded stadium. However, ZHA accused his plans of sharing “remarkable similarities with our original detailed stadium layout and our seating bowl [configuration].”

ZHA director Patrik Schumacher later described the whole saga as “incredibly distressing” and "the biggest setback ever."

In an exclusive interview with CLAD, which will appear in the forthcoming issue of CLADmag, Kuma defended his design and said that while there are some “unavoidable” similarities – such as the evacuation points, the position of the stairs and the layout of the field – his vision for the project “is totally opposite” the one proposed by ZHA.

“The communication between Zaha, the Japanese partners and the client was very bad,” he said. “I think it’s a problem in Japan. For foreign architects to work here is not easy because the system is totally different and a language barrier exists between the Japanese and the foreigners.

“Zaha was very much frustrated with that kind of miscommunication. I understand that difficulty, of course. But I was not happy to hear the claims about our scheme.”

The Japanese architect said his stadium, and the 2020 Games more broadly, will symbolise today’s Japan: a country “whose culture and direction is totally opposite from what went before” due to a slowing down of both economic growth and the pace of life.

“This new direction can be called the age of maturity,” he said. “People are finding a new, slower kind of lifestyle. But slowdown is not bad. Slowdown is creating new types of culture, new types of lifestyle. For the stadium, I have used a lot of wood because I think it’s an appropriate material to symbolise this change.”



Connect with
Leisure Management
Magazine:
View issue contents
Sign up:
Instant Alerts/zines

Print edition
 

News headlines
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways
Global industry organisations join forces to call for physical activity to be embedded into GLP-1 care pathways   15 Jun 2026

International industry lobbying associations are calling for physical activity and strength training to be deeply integrated with GLP-1 .... more>>

Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion
Barons Eden rebrands to Hiddenwell ahead of spa hotel portfolio expansion   15 Jun 2026

Barons Eden, the UK parent company that operates luxury destination properties in England, has rebranded to become .... more>>

Les Mills calls on the industry to support UNICEF
Les Mills calls on the industry to support UNICEF   12 Jun 2026

Global group exercise specialist, Les Mills, is inviting operators to sign up to its Workout for the World event on 20 June, in support of .... more>>

Belgin Aksoy prepares to mark 15 years of Global Wellness Day on Saturday 13 June
Belgin Aksoy prepares to mark 15 years of Global Wellness Day on Saturday 13 June   12 Jun 2026

Global Wellness Day (GWD) will mark its 15th anniversary on Saturday 13 June 2026, with the theme: #JoyMagenta – a celebration of the healing .... more>>

HUM2N launches longevity clinic at Six Senses London
HUM2N launches longevity clinic at Six Senses London   12 Jun 2026

Global luxury hospitality brand, Six Senses, has partnered with longevity healthcare provider, HUM2N, to launch a clinic at Six Senses London, at .... more>>

Mayrlife opens first hotel day clinic in partnership with Rosewood Vienna
Mayrlife opens first hotel day clinic in partnership with Rosewood Vienna   11 Jun 2026

As part of its first hotel partnership, Mayrlife – the medical health resort company known for its site in Altaussee, Austria – has launched a day .... more>>

Company profile


Perfect Gym Solutions S.A.

Perfect Gym, part of the Sport Alliance group, is a global software provider specialising in fitness and recreation facility management solutions and is trusted by over 1,500+ sites across 55+ countries.

View full profile>>

Catalogue gallery


Featured Supplier

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Glow beyond protection: meet Comfort Zone Hydramemory Hybrid Glow SPF 30

Sun protection is no longer just about shielding the skin – it's about enhancing it. More>>




in this issue

• Virgin gets right to wipe out rent arrears
• Fitness industry mourns passing of Jan Spaticchia
• STA offers mindfulness resources



Latest jobs

Jobs Search



Community Activator Coach Apprentice
Salary: 16,686
Location: Stowmarket, Suffolk
Company: Everyone Active
Membership Advisor
Salary: Competitive salary plus commission & benefits
Location: Market Rasen
Company: Everyone Active
Customer Service Advisor
Salary: Competitive
Location: Market Rasen
Company: Everyone Active
Diary dates
Powered by leisurediary.com

15-18 Jun 2026

HLTH Europe

RAI Convention Centre, Amsterdam, Netherlands







Published by Leisure Media Tel: +44 (0)1462 431385 | Contact us | About us | © Cybertrek Ltd